"This is the immediate next step," Tiffany Hacker, a spokeswoman for the MRC, told IRIN on 20 April from Vientiane. "Although countries were unable to reach a conclusion [to proceed with the dam], they agreed that it needed to be taken to the ministerial level."
On 19 April, officials from Thailand, Cambodia, Laos and Vietnam gathered in the Lao capital to discuss the impact of the US$3.8 billion Xayaburi dam, the first of a series of proposed hydropower dams along the river.
"This is the spirit of Mekong cooperation - member countries have consulted for the past six months, and whereas they could not come to a common conclusion in yesterday's meeting, they will continue to work together at the ministerial level until a consensus is reached," Hacker said.
The MRC's ministerial council generally meets once year in October or November. However, a special session for the Xayaburi project may be held before then, she added.
Welcome decision
The announcement was welcomed by environmentalists who say the dam would have devastating environmental, social and economic consequences.
"We are pleased to see that Thailand, Cambodia and Vietnam have recognized the trans-boundary impacts of the project and the need for further research and public consultation," Carl Middleton, a representative of the US-based environmental group International Rivers, said.
But despite the deferment, Thai media reports suggest construction of the dam by Laos has already begun, with an access road under construction since November and local residents being offered compensation of as little as $15 to relocate.
"Given the decision [on 19 April], Laos should immediately stop construction of the project and respect that the decision has been referred to a higher level," Middleton said.
Photo: Courtesy of International Rivers |
Some residents have already been told to move |
If the project goes ahead, approximately 2,100 people would be forcibly relocated and more than 200,000 would be directly affected, according to an independent review of the project commissioned by the MRC.
International Rivers says the dam could result in the extinction of approximately 41 fish species, including the critically endangered Mekong Giant Catfish, while an additional 23 to 100 migratory fish species would be threatened through a blocked fish migration route.
"These impacts in turn will affect the livelihoods and food security of millions of people in the region," the group said in a statement.
The Mekong and its tributaries provide food, water and transportation for about 60 million people in Laos, Thailand, Cambodia and Vietnam. About 40 million people are involved in the Mekong's fishery industry part-time or seasonally, according to the MRC.
Influential US Senator Jim Web has also voiced criticism of the project, saying it failed to meet international standards. "Numerous scientific studies have concluded that construction of the Xayaburi Dam and other proposed mainstream dams will have devastating environmental, economic, and social consequences for the entire Mekong sub-region," he said in a statement, adding that such dams could threaten the stability of Southeast Asia.
The Xayaburi Dam is one of 11 proposed for the lower Mekong mainstream due to increasing power demand in the region of about 6-7 percent a year, driven mainly by Thailand and Vietnam.
Both countries could face significant energy shortfalls in the near future. If built, the Xayaburi dam is expected to begin commercial operation in 2019, with about 95 percent of the project's 1,260MW capacity to be exported to Thailand.
nr/ds/mw
This article was produced by IRIN News while it was part of the United Nations Office for the Coordination of Humanitarian Affairs. Please send queries on copyright or liability to the UN. For more information: https://shop.un.org/rights-permissions