World Bank approves funding for hydropower

[Liberia] Slashed power cables dangle from wonky pylons in the Liberian capital, Monrovia. The city is still without mains electricity more than two years after the civil war ended. [Date picture taken: 10/14/2005] Claire Soares/IRIN
Uganda's workforce is set to double in the next 15 years but power supplies lag behind

The World Bank (WB) has agreed to extend to Uganda a US$360 million loan to build a controversial 250MW hydropower station on the River Nile, according to a Bank statement issued in Kampala on Friday.

The statement said the project, which has been opposed by environmentalists, would help close the country’s energy gap, which the Bank said “seriously constrains social and economic development”.

"Uganda's workforce is expected to double over the next 15 years, making the creation of jobs through expanded industry, tourism and commercial services critical," Judy O'Connor, the Bank’s country director for Uganda, said.

"These sectors are energy intensive and will therefore rely on a consistent, affordable and expanding power supply,” she noted. “Bujagali [hydropower station] is an important step towards realising the needed level and quality of supply.”

The project at Bujagali ran into trouble after environmentalists expressed concern that the dam would drown the natural falls, and urged the government to preserve the falls by opting for less harmful and cheaper energy alternatives.

They also said the falls and rapids were a significant tourism attraction and water rafting site, as well as a site of spiritual significance to the local population.

Counting the cost

The dam’s cost has been revised upwards - from $550 million to almost $800 million. On completion it is hoped the current capacity of 380MW will be increased, allowing exports to Kenya, Rwanda and Tanzania to be boosted.

If construction started immediately, the dam could be operational in 2011, re-using water flowing from two existing upstream facilities to generate electricity.

“The additional electricity will increase the supply to the national power grid at the lowest cost compared to other power generation expansion options under Uganda's energy sector strategy,” the Energy Ministry said, referring to thermal electricity.

Out of the total estimated project cost of $799 million, the Bank’s $360 million support is comprised of $130 million in loans to the private project company Bujagali Energy Ltd (BEL), $115 million from the International Development Association for the project's commercial lenders; and an investment guarantee of up to $115 million from the Multilateral Investment Guarantee Agency.

vm/cb/mw


This article was produced by IRIN News while it was part of the United Nations Office for the Coordination of Humanitarian Affairs. Please send queries on copyright or liability to the UN. For more information: https://shop.un.org/rights-permissions

Share this article

Our ability to deliver compelling, field-based reporting on humanitarian crises rests on a few key principles: deep expertise, an unwavering commitment to amplifying affected voices, and a belief in the power of independent journalism to drive real change.

We need your help to sustain and expand our work. Your donation will support our unique approach to journalism, helping fund everything from field-based investigations to the innovative storytelling that ensures marginalised voices are heard.

Please consider joining our membership programme. Together, we can continue to make a meaningful impact on how the world responds to crises.

Become a member of The New Humanitarian

Support our journalism and become more involved in our community. Help us deliver informative, accessible, independent journalism that you can trust and provides accountability to the millions of people affected by crises worldwide.

Join